top of page

NEWS

~ENR Photo Selection .jpg
13853.005.011 - small.jpg
I-95 Deck Pour 9-22-23_edited.jpg

ENR Construction Photo Contest

Yonkers Contracting is proud to have been selected for the Engineering News-Record 2023 Year in Construction Photo Contest. Out of 1,200 entries, 50 exceptional and unique photos were selected. 

Gowanus Canal CSO Facilities

Progress is happening on the Gowanus Canal Combined Sewer Overflow (CSO) Facilities project located  in Brooklyn, NY. The project is a Joint Venture of Picone and Yonkers Contracting, known as the Gowanus Canal Constructors

Deck Pour on I-95 Project Westport, CT

Concrete was placed on the first bridge deck of the I-95 Median Reconstruction and Resurfacing Project. This bridge is over Saugatuck Avenue in Westport, CT, and is one of two bridges being built parallel to I-95 that will be slid into place after the current bridge is demolished.

ACEC NJ Tolling Work Award.jpg

Yonkers Receives Two Awards

Yonkers received two awards for their work on the Port Authority of New York & New Jersey's Cashless Tolling Program from American Council of Engineering Companies of New Jersey and The New Jersey Alliance for Action.

Tracks GH1.jpg

Substantial Completion of PATH Tracks G & H Floodwall

Yonkers recently celebrated the substantial completion of the PATH Tracks G and H Flood Wall Project. Originally a Design-Bid-Build project, Yonkers ended up changing the design of the flood wall and the foundation.

GW Gantry.jpg

PANYNJ Goes Cashless

On December 11th the last of the PANYNJ's cash toll booths were deactivated at the Lincoln Tunnel. This is the final part of the agency’s upgrade to a new state-of-the-art tolling system utilizing the automatic all-cashless toll collection system.

DJI_0835 - edit.JPG
I-95 paving DJI_0783.jpg
DJI_0876.JPG
dji_export_1646402017253.jpg

Stamford Parking Garage Design-Build Project

Yonkers is the Design-Builder for the Stamford Parking Garage project. The garages’ footprint sits in an urban neighborhood nestled between I-95 and Metro-North Railroad, and elevated above South State Street. 

Yonkers Finishes I-95 Project Early and $1M Under Budget

Yonkers recently completed the NYS Thruway Authority infrastructure improvement project on I-95 in Westchester County. The project was completed ahead of schedule and approximately $1 million under its original $19.9 million contract value.

Substantial Completion of $95 Million Yonkers Newburgh-Beacon Bridge Project

The substantial completion of this Yonkers project is nine months ahead of the original schedule. The project, which started in December 2020, was originally scheduled for completion in summer 2023.

Newburgh-Beacon Bridge (I-84) Over Hudson River

Yonkers has recently completed steel strengthening and bridge deck replacement at the Newburgh Beacon Bridge North Span for the New York State Bridge Authority. This included a composite steel and concrete grid deck, concrete barrier with granite curb.

gw-bridge.jpg
report.jpg
borough-based-project-1.jpg

GWB, Cashless Tolling Infrastructure July 2022

The GWB requires infrastructure work including gantries; structural foundations; temporary and permanent traffic signage; civil, power, and communications work; and infrastructure work for the conversion of conventional tolling operations to open road cashless tolling.

First Six Months of 2022

Yonkers had a very successful first half of 2022, with contract awards for five highway and bridge projects for New York State DOT and Connecticut DOT, and a Design-Build Substation project at JFK Airport for the Port Authority, and a Substation Replacement project for PATH In New Jersey.

NYC Borough Based Jails Design-Build Program – Bronx Site Preparation

The Bronx Jail Preparation site is bordered by E 142nd Street to the north, E 141st Street to the south, Concord Avenue to the west, and Bruckner Boulevard and Southern Boulevard to the east. The site is also adjacent to the underground MTA No. 6 Subway.  

BUILDING QUALITY SINCE 1945

bottom of page